LGOIMA [1574538] Request Date: 19th February 2026
Re: 20053 – Shirley Community Centre/Facility Rebuild
Could you please provide me with the following information (from 2012 to 2026):
1. Budget Allocated – Financial Year, Annual Plan, Long Term Plan
2. Budget Spent – Year, Amount, Item Description
LGOIMA [1574538] Response Date: 12th March 2026
On 19 February 2026 you requested the following information under the LGOIMA:
“20053 – Shirley Community Centre/Facility Rebuild
Could you please provide me with the following information (from 2012 to 2026):
1. Budget Allocated – Financial Year, Annual Plan, Long Term Plan
2. Budget Spent – Year, Amount, Item Description”
Release of information
Please find below the information requested.

LGOIMA [1574538] Email: 12th March 2026
Thanks for your email.
The response doesn’t include the budget info for the Shirley Community Centre rebuild from 2012, as requested.
Could you please ask staff what amount was on budget each year (from the insurance claim til now, including when it was removed from the Rebuild Programme)?
LGOIMA [1574538] CCC Reply: 13th March 2026
No spend on this project between 2012 – 2024.
LGOIMA [1574538] Email: 13th March 2026
Thanks for your reply.
I was after the ‘Budget Allocated’ missing info from 2012 – 2024?
LGOIMA [1574538] CCC Reply: 13th March 2026
There was no budget allocated in those years.