South Library Report

South Library Te Kete Wānanga o Wai Mōkihi – Earthquake Repair Options
“The purpose of this report is to update Council on the findings of the pre-project investigation into the cost and scope of repair works required to address structural damage to the South Library from the 2010-2011 Canterbury earthquake sequence and bring this facility up to 100% NBS Importance Level 3; and endorse the staff recommendations.”
https://christchurch.infocouncil.biz/Open/2022/05/FPCO_20220526_AGN_7513_AT.htm#PDF2_ReportName_36726
This report was on the Christchurch City Council Finance and Performance Committee agenda for Thursday 26 May 2022, but was “adjourned to the Sustainability and Community Resilience Committee meeting at 9.30am 1 June 2022.”
https://christchurch.infocouncil.biz/Open/2022/06/SACRC_20220601_AGN_7539_AT.htm#PDF2_ReportName_36726


Deputations by Appointment Ngā Huinga Whakaritenga: 5.2 Joanna Gould
“Joanna Gould spoke in regards to Item 10. South Library Te Kete Wānanga o Wai Mōkihi – Earthquake Repair Options.
Her deputation focused on Shirley Library and the former Shirley Community Centre. She questioned the priority on South Library, when Shirley Library has issues around variety of books available and capacity. She also queried why the rebuild of the Shirley Community Centre has been delayed until 2030/31, and whether this aligns with the Council’s policies on sustainability and environmental outcomes. Her presentation slides are attached.
The Committee requested an updated NBS or engineering report on the Shirley Library.”
https://christchurch.infocouncil.biz/Open/2022/06/SACRC_20220601_MIN_7539_AT.PDF, Page 3
– Attachments: Deputation by Appointment 5.2 – Joanna Gould presentation slides
https://christchurch.infocouncil.biz/Open/2022/06/SACRC_20220601_MAT_7539.PDF#PAGE=17, Page 17-33
– 01.06.22, Item 5, Deputations by Appointment: https://councillive.ccc.govt.nz/video/10984, 13:20

According to this article (1), the Shirley Library is the second busiest suburban library in Christchurch, with Fendalton first & South Library third.
South Library includes a library, service centre, board room, meeting rooms, learning centre & cafe. South Library to Tūranga = 3.8km
Shirley Library is also considered a suburban library, but there is no board room, meeting rooms or learning centre. Shirley Library to Tūranga = 4.7km
The actual floor space allocated to the Shirley Library, is less than half of the current building.
As the Service Centre (which includes NZ Post) & the Coastal-Burwood Governance Team are also located in this building.
The ReVision Youth Audit on the Shirley Library highlights some of the issues from our youth’s perspective. (2)
Shirley/The Palms is already considered a ‘Key Activity’ area. Our population has significantly increased due to infill housing & more social housing. Yet there are no plans to upgrade the size or change the location of the current Shirley Library and Service Centre?
Greater Christchurch Our Space 2018-2048
Page 25, Key Activity Centres
Page 26, Higher Density Residential
Page 30, Future Development Areas
Page 36, 10-minute Neighbourhood for Key Centres
In the CCC Asset Management Plan Summary: Libraries (3), the South Library replacement cost is considerably less than the amount proposed in this report.
The Shirley Library replacement cost is more than the amount on budget in the proposed CCC Annual Plan, for the the rebuild of the Shirley Community Centre. (4)
Shirley Library was built in 1995. South Library was built in 2003.
South Library has 3 times the capacity of Shirley Library, yet the population density for Shirley Library is higher. (5)
Both the Shirley Community Centre & Shirley Library were included in the original CCC Facilities Rebuild programme. (6) South Library wasn’t included.
The CCC Libraries 2025 Facilities Plan (7) states that “Libraries will adhere to sustainable, long lasting design and ensure good return on investment. All planning will maximise the potential capacity of existing facilities, and take into consideration life cycle cost of new and existing building.”
“Shirley Library: Future need for more service capability. Space required to develop service for learning services to support need in the community.” Page 36
With the Shirley Library building being constructed in 1995, according to the Reference Building Type, there may be some issues in regards to the design/earthquake loads. (8)
From a potential disaster/civil defence point of view (9), building a standalone civic centre at 10 Shirley Road, opposite our largest school (Shirley Primary) would also provide a central meeting place/emergency location (with solar panels & rainwater harvesting system), away from The Palms (which closed for over six months due to earthquake repairs). (10)
In the South Library report under Defer the repair/rebuild, Disadvantages: “Despite its high use, it is not at the same standard as other libraries of similar size and function with the building services at/or near end of life.”
This statement applies more to Shirley Library than South Library. As in the South Library report, under Functionality: [South Library] “facility provides sufficient floor area”, which is not the case with the current Shirley Library.
The Local Government Community Well-being Act (11) addresses four aspects: Social, Economic, Environmental & Cultural: “As the operational arm of government, councils deliver infrastructure vital to our economy, such as roads, three waters and housing infrastructure, cultural and social amenities such as events, parks, libraries…”
In my PowerPoint presentation, I’ve included images of the view from the current Shirley Libary, looking into The Palms car parking. (12)
What impact do you think this view has on our communities wellbeing?
Do these images align with the Council’s Asset Management Plan for Libraries?
Residents have been asking since 2012 for a new building at 10 Shirley Road, to replace the former Shirley Community Centre that was demolished after the earthquakes. (13)
There is still no suburban library in the Innes Ward. Yet the current Innes Ward boundaries have significantly decreased in size, as the population continues to grow.
Christchurch City Council Development Contributions Policy 2021
Page 6: 1.3.1 Strategic reasons “The Council’s vision statement, community outcomes and strategic priorities constitute the Council’s Strategic Framework which guide decisions made by Council with a focus on improving overall community wellbeing.”
1.3.2 Fairness and equity “Christchurch City Council has decided it will use development contributions as the primary method of funding growth-related infrastructure. This approach enables the cost of providing growth infrastructure to be funded primarily by those who cause and/ or benefit from that investment.”
Page 8: “The Council will fund the growth capacity of the following types of community infrastructure from development contributions for community infrastructure: Libraries.
Development contributions for community infrastructure are levied on a district-wide basis, meaning the development contribution charge will be the same regardless of development location within the Christchurch District.”
After reading this report on the South Library, I do not understand why the Council would prioritise the repair/rebuild of the South Library.
The South Library is still in operation. The Shirley Community Centre was demolished. The current Shirley Library isn’t fit for purpose & does not meet the needs of our growing population.
This proposal doesn’t align with the Christchurch City Council’s policies on sustainability and environmental outcomes. (14) (15)
There are suburbs across the city that are lacking community facilities. (16)
The communities around Shirley Road have been waiting since 2012 for a new building to be built on 10 Shirley Road. Why has the Christchurch City Council deferred funding this until 2030/31? (17)
In my view, the Council should not direct staff to engage with renewals, while existing rebuilds have not been completed.

References:
(1) https://www.stuff.co.nz/the-press/news/128047707/earthquake-repairs-spell-18month-closure-of-popular-christchurch-library
(2) https://christchurch.infocouncil.biz/Open/2021/12/YTAC_20211201_AGN_5468_AT.PDF, Page 20-37
(3) https://ccc.govt.nz/assets/Documents/The-Council/Plans-Strategies-Policies-Bylaws/Plans/Long-Term-Plan/LTP-2021-final/Asset-Management-Plan-AMP-Libraries-LTP-2021-2031.PDF, Page 66
(4) https://ccc.govt.nz/assets/Documents/The-Council/Plans-Strategies-Policies-Bylaws/Plans/Long-Term-Plan/LTP-2021-final/LTP-2021-Final-Activity-Plan-Community-Development-and-Facilities.PDF, Page 21
(5) https://ccc.govt.nz/assets/Documents/The-Council/Plans-Strategies-Policies-Bylaws/Plans/Long-Term-Plan/LTP-2021-final/Asset-Management-Plan-AMP-Libraries-LTP-2021-2031.PDF, Page 70, Libraries Sites
(6) https://ccc.govt.nz/assets/Documents/The-Rebuild/Community-facilities/CommunityFacilitiesTranche1.pdf
(7) https://christchurchcitylibraries.com/2025/Libraries2025FacilitiesPlan-2008.pdf
(8) https://ccc.govt.nz/assets/Documents/The-Rebuild/Community-facilities/ShirleyLibraryL5.pdf, Page 7
(9) “Building Community Resilience: Learning from the Canterbury earthquakes”
Appendix 2: Shirley Case Study Report, Page 73-85
https://hauora.co.nz/assets/files/Resources/Final%20Report%20to%20HRC%20-%20Building%20Community%20Resilience.pdf
(10) https://www.stuff.co.nz/the-press/5587428/The-Palms-reopens-after-quake-repairs
(11) https://www.lgnz.co.nz/news-and-media/2019-media-releases/reinstated-well-beings-endorse-councils-community-focus/
(12) https://www.10shirleyroad.org.nz/wp-content/uploads/2022/06/SouthLibraryEarthquakeRepairOptionsReportJoannaGould.pdf, Page 13
(13) https://www.10shirleyroad.org.nz/where-is-our-community-centre-petition/
(14) https://ccc.govt.nz/assets/Documents/The-Council/Plans-Strategies-Policies-Bylaws/Policies/ChristchurchCityCouncilSustainabilityPolicy2008-sustainabilitychristchurch.pdf
(15) https://ccc.govt.nz/the-council/plans-strategies-policies-and-bylaws/policies/accessibility-policies/equity-and-access-for-people-with-disabilities-policy/
(16) https://smartview.ccc.govt.nz/map/layers/communityfacility#/@172.65355,-43.50796,14
(17) https://ccc.govt.nz/assets/Documents/The-Council/Plans-Strategies-Policies-Bylaws/Plans/Long-Term-Plan/LTP-2021-final/LTP-2021-Final-Activity-Plan-Community-Development-and-Facilities.PDF, Page 21


South Library Te Kete Wānanga o Wai Mōkihi – Earthquake Repair Options: Minutes
– Committee Comment:
1. Amendments were put forward that provided additional details to the Officer
Recommendations, along with extending Council consideration of the development and costings on design from Q1 2023 to Q2 2023 and assessing options for a temporary facility during the rebuild phase.
2. The Committee requested that when Officers come to Council with the concept design and costings in Q2 2023, that information about extending temporary strengthening of the building is provided as a comparator and made publically available, along with cost implications and associated risks.
– Officer Recommendations:
That the Sustainability and Community Resilience Committee:
1. Direct staff to progress the design for a rebuild of the South Library Facility on its
existing site.
2. Endorse the development of a concept design and costing for consideration by Council in Q1 2023.
3. Note that the advancement of the project to construction will require additional funding in Annual Plan 2023-2024 and or a Long Term Plan adjustment.
– Amendment moved by Councillor Scandrett and seconded by Councillor Coker
That the Sustainability and Community Resilience Committee:
1. Direct staff to progress the design for a rebuild of the South Library Facility on its existing site.
a. Include the public throughout the design process, seeking ideas and then feedback
prior to endorsement of the concept design.
b. Request that the rebuild is done to high sustainability standards including carbon
emissions and water use, both during the construction and operation of the library.
https://christchurch.infocouncil.biz/Open/2022/06/SACRC_20220601_MIN_7539_AT.PDF, Page 6


10 Shirley Road’ Pages & Blog Posts:
CCC Draft Annual Plan 2022-2023 Submission
Shirley Centre Concept 2021
CCC 10 Shirley Road Consultation Feedback
Poto Williams Support Letter
Duncan Webb Support Letter
“Where is our Community Centre” Petition
Proposed Pump Track for Shirley
Timeline

Links:
Warren and Mahoney: South Christchurch Library and Service Centre
Christchurch City Council Facilities rebuild: Engineering reports
Christchurch City Council: South Library Engineering Report
Christchurch City Council: Shirley Library Engineering Report
Christchurch City Council Long Term Plan 2021-31 Activity and Asset Management Plans
Christchurch City Council Asset Management Plan Summary: Libraries
Christchurch City Council Asset Management Plan Summary: Community Facilities
Christchurch City Libraries 2025 Facilities Plan
Christchurch City Libraries Events: Shirley
Christchurch City Council Development Contributions Policy 2021
Christchurch City Council Sustainability Policy 2008
Christchurch City Council Equity and Access for People with Disabilities Policy
Christchurch City Council Build Smarter Guides and Resources
Christchurch City Council SmartView: Community Facilities
Christchurch City Council SmartView: EV Charging stations
Christchurch City Council: Innes Ward (current)
Christchurch City Council: Innes Ward (new/2022 election)
Greater Christchurch Our Space 2018-2048
Christchurch City Council Community Facilities Rebuild Tranche 1
Christchurch City Council Community Facilities Rebuild Tranche 2
Canterbury Stories: The Palms Earthquake Photos
Canterbury Stories: Fences and containers at Shirley Library
Christchurch City Libraries: Shirley Library History
CCC ‘Have Your Say’ Your ideas wanted for 10 Shirley Road

News Articles:
Council votes to rebuild South Library in Christchurch (6 June 2022)
Rebuilding South Library cheaper than repair (6 June 2022)
Popular Christchurch library to be demolished and rebuilt (1 June 2022)
Concept plans to be drawn-up for new South Library and Service Centre (1 June 2022)
Council staff propose to demolish and rebuild busy Christchurch library (20 May 2022)
Rebuild on the cards for quake-damaged South Library and Service Centre (20 May 2022)
Large investment portfolio for sale next to popular Christchurch shopping centre (21 March 2022)
Earthquake repairs spell 18-month closure of popular Christchurch library (16 March 2022)
New owners take over Christchurch’s The Palms shopping mall (23 November 2021)
Christchurch shopping centre sale highlights New Zealand’s compelling retail investment fundamentals (23 November 2021)
Study to determine feasibility of Christchurch community centre (16 July 2021)
Renewed calls to rebuild Shirley Community Centre (1 December 2020)
Brief closure heralds service boost for Shirley Library and Service Centre (9 March 2020)
Green light for pump track (24 September 2019)
Law change reinforces Councils’ community focus (8 May 2019)
Reinstated well-beings endorse councils’ community focus (8 May 2019)
Call For Community Facility Grows (10 May 2018)
Is Shirley Christchurch’s forgotten suburb? (4 May 2018)
Christchurch suburb overlooked since the earthquakes, community leaders say (30 April 2018)
Community centre builds delayed (26 October 2016)
Community Centre in Shirley Stalled (19 July 2016)
$40m to rebuild community, heritage facilities in Chch (4 September 2014)
Councillors back Shirley community site (16 August 2013)
New community centre planned for Shirley (16 August 2012)
The Palms reopens after quake repairs (8 September 2011)

Shirley Centre Concept 2021

PDF: Shirley Centre Concept 2021 by Joanna Gould

Page 1: Shirley Centre | Overview
– 1.1 Shirley Centre | Overview: Shirley Centre at 10 Shirley Road
– 1.2 Shirley Centre | Overview: Learning Libraries Concept
– 1.3 Shirley Centre | Overview: Research/Ideas/Submissions

Page 2: Shirley Centre | Location
– 2.1 Shirley Centre | Location: Suburbs surrounding 10 Shirley Road, Innes Ward Deprivation Index, SmartView Community Facilities
– 2.2 Shirley Centre | Location: Projected Population, CCC District Planning Maps 25 & 32
– 2.3 Shirley Centre | Location: CCC & Ōtautahi Community Housing Trust, Kāinga Ora (Housing New Zealand)

Page 3: Shirley Centre | CCC District Plan
– 3.1 Shirley Centre | CCC District Plan: Planning Maps for 10 Shirley Road
– 3.2 Shirley Centre | CCC District Plan: Zones and Designations for 10 Shirley Road
– 3.3 Shirley Centre | CCC District Plan: Other Notations
– 3.4 Shirley Centre | CCC District Plan: Natural and Cultural Heritage

Page 4: Shirley Centre | Site History
– 4.1 Shirley Centre | Site History: Shirley Road History
– 4.2 Shirley Centre | Site History: Significant Park Trees
– 4.3 Shirley Centre | Site History: Dudley Creek
– 4.4 Shirley Centre | Site History: Chancellor Street Heritage Houses
– 4.5 Shirley Centre | Site History: Dudley Character Area
– 4.6 Shirley Centre | Site History: Shirley Playcentre (back right corner of the Shirley Community Reserve)

Page 5: Shirley Centre | Original Building
– 5.1 Shirley Centre | Original Building: Shirley Primary School
– 5.2 Shirley Centre | Original Building: George Penlington (CEB Architect for Shirley Primary & Richmond Schools)
– 5.3 Shirley Centre | Original Building: Shirley Community Centre
– 5.4 Shirley Centre | Original Building: NZ Society of Genealogists – Canterbury Branch

Page 6: Shirley Centre | CCC Community Facilities
– 6.1 Shirley Centre | CCC Community Facilities: CCC Community Facilities Network Plan
– 6.2 Shirley Centre | CCC Community Facilities: Christchurch City Libraries
– 6.3 Shirley Centre | CCC Community Facilities: St Martins Community Centre
– 6.4 Shirley Centre | CCC Community Facilities: Redcliffs Village Library
– 6.5 Shirley Centre | CCC Community Facilities: Sumner Centre

Page 7: Shirley Centre | Learning Libraries
– 7.1 Shirley Centre | Learning Libraries: CCC Architectural Awards
– 7.2 Shirley Centre | Learning Libraries: Community Education & Support Services in Learning Libraries
(Community Education: “Well-being WOF/Tool Kit”, Community Education: “While You Wait”, Community Education: “Climate Change 101”)

Page 8: Shirley Centre | Concept

Page 9: Shirley Centre | Design Considerations
– 9.1 Shirley Centre | Design Considerations: Universal
– 9.2 Shirley Centre | Design Considerations: Cultural
– 9.3 Shirley Centre | Design Considerations: Autism Spectrum Disorder (ASD) & Sensory Processing
– 9.4 Shirley Centre | Design Considerations: Biophilic
– 9.5 Shirley Centre | Design Considerations: Environmental & Sustainable

Page 10: Shirley Centre | Design Inspiration
– 10.1 Shirley Centre | Design Inspiration: George Penlington
– 10.2 Shirley Centre | Design Inspiration: Benjamin Oakes Moore
– 10.3 Shirley Centre | Design Inspiration: Māori Culture: Te Pae Māhutonga
– 10.4 Shirley Centre | Design Inspiration: Māori Culture: Te Whare Tapa Whā
– 10.5 Shirley Centre | Design Inspiration: Māori Culture: Whakairo (Carving)

Page 11: Shirley Centre | Building Ideas
– 11.1 Shirley Centre | Building Ideas: Building
– 11.2 Shirley Centre | Building Ideas: Interior

Page 12: Shirley Centre | Landscape Ideas
– 12.1 Shirley Centre | Landscape Ideas: Current Site Map
– 12.2 Shirley Centre | Landscape Ideas: Internal Courtyard (centre of the First Floor)
– 12.3 Shirley Centre | Landscape Ideas: Natives Garden (by Dudley Creek)
– 12.4 Shirley Centre | Landscape Ideas: Wellbeing Sensory Garden (front left)
– 12.5 Shirley Centre | Landscape Ideas: Basketball Area (front right)
– 12.6 Shirley Centre | Landscape Ideas: Playground

CCC Draft Annual Plan 2022-2023 Submission

Christchurch City Council Draft Annual Plan 2022/23
Have your say on a budget which focuses on doing the basics well and strengthening Ōtautahi Christchurch’s infrastructure.
Open for feedback: 11th March 2022 – 18th April 2022
https://www.ccc.govt.nz/the-council/haveyoursay/show/494

Christchurch City Council Draft Annual Plan 2022-2023
Written Submission by Joanna Gould

PDF: CCC Draft Annual Plan 2022 Submission by Joanna Gould | April 2022
– Page 1: Shirley Community Centre Rebuild
– Page 2: Waipapa Papanui-Innes Community Board
– Page 3: Christchurch City Council – CPTED, LTP 2021-31 Activity & Asset Management Plans
– Page 4: Christchurch City Council – Integrated Planning Guide
– Page 5: Christchurch City Libraries – Architecture & Design Study
– Page 6: ReVision Youth Audit Shirley Library
– Page 7: Learning Libraries Concept
– Page 8: Shirley Centre Concept
– Page 9: Instore Demonstration Concept

Christchurch City Council Draft Annual Plan 2022-2023
Verbal Submission by Joanna Gould

https://councillive.ccc.govt.nz/video/10927
PowerPoint Presentation by Joanna Gould
PDF: CCC Draft Annual Plan 2022 PowerPoint Presentation by Joanna Gould | May 2022
– Page 1: 10 Shirley Road, You Are Here
– Page 2: Original Idea (2018) Page 1 | https://www.10shirleyroad.org.nz/centre-ideas/
– Page 3: Original Idea (2018) Page 2 | https://www.10shirleyroad.org.nz/centre-ideas/
– Page 4: 10 Shirley Road: Pre Earthquakes, Post Earthquakes, Today 2022
– Page 5: “Where is our Community Centre” Petition | https://www.10shirleyroad.org.nz/where-is-our-community-centre-petition/
– Page 6: Letter of Support from Poto Williams & Duncan Webb | https://www.10shirleyroad.org.nz/poto-williams-support-letter/ & https://www.10shirleyroad.org.nz/duncan-webb-support-letter/
– Page 7: Local Government Act Community Well-being Amendment Bill (2019)
– Page 8: The Palms car park entrance & Shirley Library view into car park (top) & street views of the Shirley Library (bottom)
– Page 9: 10 Shirley Road site with significant trees/playground/half basketball court opposite Shirley Primary School & Shirley Playcentre (top), Chancellor Street Heritage Houses & Dudley Creek pathway (bottom)
– Page 10: 10 Shirley Road site opposite Shirley Primary School & existing car park with Dudley Creek pathway (top), entrance to 10 Shirley Road site with signalised pedestrian crossing/bus stops either side of Shirley Road (bottom)
– Page 11: Shirley Centre: Identity | Well-being | Learning. Community Education & Support Services in Learning Libraries. New Shirley Community Centre: Library, Service Centre, Learning Spaces, Playground with Shirley Playcentre.

Shirley Road Central

The idea for this group came about while advocating for a new centre at 10 Shirley Road.

We can’t keep waiting for a new building to be built, because what could happen inside this building, is needed now:
a citizen hub for community connections, community directory, sharing resources, promoting activities/events/organisations, community education…

So instead of waiting for a ‘physical’ building to be built, we are creating an online community first, to connect communities around Shirley Road: Shirley, Dallington, Richmond, Edgeware, St Albans & Mairehau.

‘Shirley Road Central’ Website:
https://www.shirleyroadcentral.nz/
Directory: https://www.shirleyroadcentral.nz/src-directory/
Activities: https://www.shirleyroadcentral.nz/src-activities/
Blog Posts: https://www.shirleyroadcentral.nz/src-blog-posts/
Support Services: https://www.shirleyroadcentral.nz/src-support-services/

‘Shirley Road Central’ Facebook Page:
https://www.facebook.com/shirleyroadcentral/
Online Community Directory & Community Education

‘Shirley Road Central’ Facebook Group:
https://www.facebook.com/groups/shirleyroadcentral/
Online Noticeboard & Community Discussions

Why ‘Shirley Road Central’?
https://www.shirleyroadcentral.nz/shirley-road-central/

CCC Long Term Plan 2021 Submission

PDF: CCC Long Term Plan 2021 Submission by Joanna Gould | April 2021

Christchurch City Council Long Term Plan 2021-31
Written Submission by Joanna Gould

1. Shirley Centre | Location
1.1 Suburbs surrounding 10 Shirley Road, Innes Ward Deprivation Index, SmartView Community Facilities
1.2 Projected Population, CCC District Planning Maps 25 & 32
1.3 CCC & Ōtautahi Community Housing Trust, Kāinga Ora (Housing New Zealand)
1.4 Nearest Bus Stops/Routes to Papanui/Aranui/Parklands/New Brighton Libraries, Nearest Bus Stops/Routes to Shirley Library, Bus Routes Network Map, Nearest Bus Stops/Routes Bus Routes to 10 Shirley Road, Bus Routes to Local Community Centres
1.5 Route from Local Schools to 10 Shirley Road, Local Schools Info, Local Schools Development Plans
1.6 EnviroSchools
1.7 CCC Have Your Say Consultation: Engagement Feedback for 10 Shirley Road Report
2. Shirley Centre | Learning Libraries
3. Shirley Centre | Legacy


Christchurch City Council Long Term Plan 2021-31
Verbal Submission by Joanna Gould

https://councillive.ccc.govt.nz/video/9942
N.B. Don’t try reading from your phone, if you have problems focusing due to your eyesight. Lesson learnt: write your verbal submission down on paper, so it’s easier to read…

Our Christchurch ancestors created a place for learning, the original Shirley Primary School at 10 Shirley Road in 1915, which later was turned into the Shirley Community Centre.
This building became part of our communities identity and our own memories, until it was demolished in 2012.

Our suburbs have had a significant increase to our population due to new residential/infill housing/social housing since the CCC District Plan has been changed after the earthquakes, but no new community facilities are on budget in the proposed CCC LTP plan?

The Council collects significant Development Contributions from our suburbs “to recover the costs of providing future growth capacity for facilities such as swimming pools, sports centres, libraries”, that need investing back into our community.

Yesterday Councilor Chen asked our Community Board what impact a new centre would have on rates. The impact should be cost neutral.
The sale proceeds of the “potential Disposal of Council Owned Properties”: the four properties: 114 Hills Road, 219A Hills Road, 79 Slater Street & 81 Slater Street, could be invested in building a new centre at 10 Shirley Road.

We have collected over 1,000 signatures with our petition, which we will be presented formally in the coming weeks.
We have a letter of support from Poto Williams, our MP for Christchurch East.
The residents in our communities wants this, but it is also needed.

This location is a very visible historic landmark at the beginning of Shirley Road. Leaving it empty without a community centre, is a constant reminder of what we have lost, that we have been forgotten & have no community legacy for the future generations and clearly not what our ancestors intended for their future generations: us.

We are asking you to instruct staff to put a plan in place to deliver a new centre in this Long Term Plan term.

We need a multi cultural civic facility, not faith based, not captured by loud voices in the community, something owned and managed by our Council for all the communities connected to Shirley Road.